📋 This is an example project roadmap — see how we keep you informed every step of the way
Bioclean Disaster Services

ROADMAP

Helping you get back to your life

123 Example Street

Client: Example Client

Messages

Your Project ManagerMar 20, 2026

The asbestos samples our crew had collected have been sent to the lab this morning. If you have any questions please contact Your Project Manager at ProjectManager@biocleandisaster.ca or 587-605-1067.

Day 1
1-7 DAYS

Bioclean collects client info

Day 1

Bioclean arrives to assess damage

Day 2

Bioclean sends 12-hour report to insurance

Bioclean Truck
Day 2-3

Possible delay if asbestos testing is required

5
Day 3

Insurance confirms coverage

6
Day 3-4

Emergency work begins

7
Day 4-5

Flooring samples sent for evaluation

8
Day 5-7

Emergency estimate sent to insurance company

9
Day 7-8
7-14 DAYS

Project manager reports budget to insurance

10
Day 8-9

Bioclean Contents Team determines what can be cleaned

Day 9-10

Insurance approval needed to continue

12
Day 10-11

Homeowner selects flooring

Day 11-12

Possible delay if flooring isn't chosen

14
Day 12-14

Schedule rebuild

15
Day 21+

Home specialist meets with homeowner

16
Week 4

Review budget, upgrades, and changes

Week 4-6

Process may be slowed by delay in decision making

18
Week 6-8

Homeowner finalizes selection of paint and finishes

19
Week 8-10

Change orders to be signed

Week 10

Delay if change orders are required and not signed

21
Week 10-12

Rebuild starts

22
Month 1-2

Schedule of loss, which contents can be replaced

23
Month 2

Flooring acclimatization, drywall/paint repairs require multiple visits

24
Month 3

Rebuild sign off

25
Completion

Contents returned

Overall Progress13%
Stage 4 of 25Possible delay if asbestos testing is required

1-7 DAYS

  • • Emergency Process
  • • Weekly Communications
  • • Emergency Estimate Sent
  • • Asbestos Testing Required On Houses Built Prior To 1990

7-14 DAYS

  • • Contents Cleaning Estimate
  • • Weekly Communications
  • • Rebuild Estimate Delivered
  • • Non-Restorable List and Client Creates Budget

DAY 21 - 3 MONTHS

  • • Reconstruction Begins
  • • Weekly Communications

1-3 MONTHS TO COMPLETION

  • • Weekly Communications

POTENTIAL ROADBLOCKS:

Delay in materials
Materials arriving damaged
Weather conditions or climate changes
Major storms
Illness or personal circumstances
Questions?Call 1-833-246-8326

Ready to get started?

Our team is here to help with your restoration needs

Call Us

1-833-246-8326

Email Us

info@biocleandisaster.ca

BIOCLEAN

Disaster Services

5526 50 Avenue, Lloydminster, AB

© 2026 Created by Brooklyn Gray | Project Support Coordinator